Initialize Prometheus metrics on node start where appropriate and review
the usage of the following metrics:
```
anna@kiwi:~/Documents/GitProjects/nspcc-dev/neo-go$ find | grep prometheus.go
./pkg/network/prometheus.go
./pkg/core/stateroot/prometheus.go
./pkg/core/prometheus.go
./pkg/services/rpcsrv/prometheus.go
./pkg/services/metrics/prometheus.go
```
Close#2970.
Signed-off-by: Anna Shaleva <shaleva.ann@nspcc.ru>
The reader is about to exit and it will close legacy c.Notifications, but it
will leave subscription channels at the same time. This is wrong since these
channels will no longer receive any new events, game over.
Signed-off-by: Roman Khimov <roman@nspcc.ru>
wsReader() closes c.done first and then goes over the list of
c.respChannels. Technically this means that any of the two can be taken in
this select.
Signed-off-by: Roman Khimov <roman@nspcc.ru>
If `StartWhenSynchronized` is unset in config, `node` command runs RPC
service instantly. Previously there was a ground for deadlock. Command
started RPC server synchronously. According to server implementation, it
sends all internal failures to the parameterized error channel. Deadlock
occured because main routine didn't scan the channel.
Run `rpcsrv.Server.Start` in a separate go-routine in `startServer`.
This prevents potential deadlock caused by writing into unread channel.
Fixes#2896.
Signed-off-by: Leonard Lyubich <leonard@morphbits.io>
Previously RPC server shutdown procedure listened to the execution
channel and stopped at the first element that arrived in the queue. This
could lead to the following problems:
* stopper could steal the execution result from subscriber
* stopper didn't wait for other subscription actions to complete
Add dedicated channel to `Server` for subscription routine. Close the
channel on `handleSubEvents` return and wait for signal in `Shutdown`.
Signed-off-by: Leonard Lyubich <leonard@morphbits.io>
Previously RPC server could never be shut down completely due to
some start precondition failure (in particular, inability to serve HTTP
on any configured endpoint). The problem was caused by next facts:
* start method ran subscription routine after HTTP init succeeded only
* stop method blocked waiting for the subscription routine to return
Run `handleSubEvents` routine on fresh `Start` unconditionally. With
this change, `Shutdown` method won't produce deadlock since
`handleSubEvents` closes wait channel.
Refs #2896.
Signed-off-by: Leonard Lyubich <leonard@morphbits.io>
There is an existing problem with RPC server shutdown freeze after start
failure due to some init actions (at least HTTP listen) described in
#2896.
Add dedicated unit test which checks that `Shutdown` returns within 5s
after `Start` method encounters internal problems.
Signed-off-by: Leonard Lyubich <leonard@morphbits.io>
I've carefully checked the way how new service can be added to the
Blockchain instance or to be removed from it. Current implemention
of SetNotary and SetOracle methods doesn't contain dangerous code,
and native contracts have atomic values everywhere where service
is stored.
Current implementation of Notary, Oracle and StateRoot services'
reload/disabling/enabling on SIGUSR1 is safe and doesn't require
any adjustment.
This commit closes#2944, it's not a bug in the code, it's just
stale documentation.
Signed-off-by: Anna Shaleva <shaleva.ann@nspcc.ru>
This check is good and was present here since #1729, but it was
accidently removed from the reference implementation (see the
discussion in https://github.com/neo-project/neo/issues/2848). The
removal of this check from the C# node leaded to the T5 testnet state
diff since 1670095 heigh which causes inability to process new blocks
since 2272533 height (see #3049). This check was added back to the
C# node in https://github.com/neo-project/neo/pull/2849, but it is
planned to be the part of the upcoming 3.6.0 C# node release.
We need to keep our testnet healthy, thus, strict contract script
check will be temporary removed from the node code and is planned
to be added back to be a part of the next 3.6.0-compatible release.
Close#3049.
Signed-off-by: Anna Shaleva <shaleva.ann@nspcc.ru>
All Notary contract witnesses in incomplete transaction (both main
and fallback) may either have invocation scripts pushing dummy signature
on stack or be empty, both ways are OK. Notary actor keeps main tx's
Notary witness empty and keeps fallback tx's Notary witness filled
with dummy signature.
Signed-off-by: Anna Shaleva <shaleva.ann@nspcc.ru>
Our wrapping optimization relied on the caller context having a TRY block,
but each context (including internal calls!) has an exception handling stack
of its own, which means that for an invocation stack of
entry
A.someMethodFromEntry() # this one has a TRY
A.internalMethodViaCALL() # this one doesn't
B.someMethod()
we get `HasTryBlock() == false` for `A.internalMethodViaCALL()` context, which
leads to missing wrapper and missing rollbacks if B is to THROW. What this
patch does instead is it checks for any context within contract boundaries.
Fixes#3045.
Signed-off-by: Roman Khimov <roman@nspcc.ru>
Do not add them directly to chain, it will be done by the block queue
manager. Close https://github.com/nspcc-dev/neo-go/issues/2923. However,
this commit is not valid without
https://github.com/roman-khimov/dbft/pull/4.
It's the neo-go's duty to initialize consensus after subsequent block
addition; the dBFT itself must wait for the neo-go to complete the block
addition and notify the dBFT, so that it can initialize at 0-th view to
collect the next block.